New Construction Plans Review, Inspections, and Approval Process

Fire Prevention Project Phases

Phase 1Initial Plans submitted by Developer for completeness reviewProject Starts
Phase 2Fire Prevention Detailed Plans ReviewRequired revisions
Phase 3Final Inspections and Certificate of Occupancy ApprovalCompletion
PhasesTimeline TargetsTotals
Phase 1Five (5) Business Days*  5
Phase 2Ten (10) Business Days* Detailed Plans ReviewFive (5) Business Days* Negotiations/RevisionsFive (5) Business Days* Revisions Review20
Phase 3Five (5) Business Days* Inspections/TestingOne (1) Business Day* Reinspection 6
   Goal:31 Days

*KCKFD Timelines are dependent upon developer revision submissions. Our time clock stops when the plans are returned back to Developer for revisions through the DRC coordinator. The timeline standards represented here are the amount of time needed for the Fire Prevention Division to complete our work. Time spent with developer for revisions is not the responsibility of KCKFD. Additional contractor revisions extend the total timeline for plans review.

November 2024 Status Report