New Construction Plans Review, Inspections, and Approval Process
Fire Prevention Project Phases
Phase 1
Initial Plans submitted by Developer for completeness review
Project Starts
Phase 2
Fire Prevention Detailed Plans Review
Required revisions
Phase 3
Final Inspections and Certificate of Occupancy Approval
Completion
Phases
Timeline Targets
Totals
Phase 1
Five (5) Business Days*
5
Phase 2
Ten (10) Business Days* Detailed Plans Review
Five (5) Business Days* Negotiations/Revisions
Five (5) Business Days* Revisions Review
20
Phase 3
Five (5) Business Days* Inspections/Testing
One (1) Business Day* Reinspection
6
Goal:
31 Days
*KCKFD Timelines are dependent upon developer revision submissions. Our time clock stops when the plans are returned back to Developer for revisions through the DRC coordinator. The timeline standards represented here are the amount of time needed for the Fire Prevention Division to complete our work. Time spent with developer for revisions is not the responsibility of KCKFD. Additional contractor revisions extend the total timeline for plans review.